Single-phase electricity meter – Mercury 203


Description, model range, marking of the Mercury electricity meter

Among electricity metering devices, the most popular in Russia and the CIS countries is the range of electric meters produced under the Mercury brand. These devices have practically replaced morally and technically obsolete devices from service. The information collected in the article will be useful to those who are planning to purchase and install a pulse electric meter, but cannot make a choice. In addition, we will give examples of connection diagrams for single-phase and three-phase devices, and also talk about the features of their operation.

Model range and markings

Metering devices manufactured by Incotex are available in the following modifications:

  • 100 is a model range of single-phase single-tariff mechanical electric meters of direct connection. The characteristic features of such devices are simplicity of design and low cost.


    Model CE 101

This model range is currently discontinued and is being replaced.

  • 200 – devices of the second generation, produced in single-phase and three-phase versions. Modifications are being made to allow remote readings to be taken in two-tariff (day-night) and single-tariff modes. For this purpose, a special module (for example, a GSM modem) is built into the device, transmitting information to the appropriate service. Below is a table where, for clarity, several modifications from this model range are given with a description of the main technical characteristics.

Table 1. Example of abbreviated technical parameters of various devices of the 200 model series.

ModelUNOM (V)Rated and (maximum) current (A)Active/reactive energy measurement accuracy classNumber of tariffs
201 2240,05,0 (60,0)11
202 5240,05,0 (60,0)11
203 1240,05,0 (80,0)11
205 FION240,05,0 (60,0)1 / 24
206 PRNO240,05,0 (60,0)1 / 24
230 AKE3x240.0/3805,0 (60,0)1 / 22
230 ART 01 PQRSIN3x240.0/3805.0 (60.0)1 / 24
230 ART 02 PQRSIDN3x240.0/38010,0 (100,0)1 / 24
231 AM 013x240.0/3805.0 (60.0)11
233 ART 03 KRL3x240.0/38010,0 (100,0)1 / 24
236 ART 02 RS3x240.0/38010,0 (100,0)1 / 24

As can be seen from the table using the example of the 230 model, the plant can produce several modifications of the device. To define them, special characters are used, they are given below.


Designation of modifications using symbols

Now it will not be difficult to decipher the markings of any Mercury device. For example, the marking 230 AR 01 r 5 60 a 380v means that this is a 3-phase electric meter that allows you to measure the consumption of active and reactive energy. The device is designed to operate with a rated voltage of 380 V and a current of 5-60 A (nominal and maximum value).

Price for Mercury 230 counters

ModelQtyPrice in rubles
Meter Mercury 230 AR-00 C (R) 5(7.5)PC2000
Meter Mercury 230 AR-01 C (R) 5(50) LCDPC2200
Meter Mercury 230 AR-02 C (R) 10(100) LCDPC2310
Meter Mercury 230 AR-03 C (R) 5(7.5)PC2450
Meter Mercury 230 ART-00 P(Q)С(R)SIDN 5(7.5)PC2840
Meter Mercury 230 ART-01 P(Q)C(R)SIN 5(60)PC2698
Meter Mercury 230 ART-02 P(Q)C(R)SIN 10(100)PC3500
Meter Mercury 230 ART-03 P(Q)C(R)SIDN 5(7.5)PC3650
Meter Mercury 230 ART-00 C (R) N 5(7.5) tariffPC3670
Meter Mercury 230 ART-01 C (R) N 5(50) tariffPC3900
Meter Mercury 230 ART-02 C (R) N 10(100) tariffPC3200
Meter Mercury 230 ART-03 C (R) N 5(7.5) tariffPC3500
Meter Mercury 233 ART-00 KRR 5(10)PC6100
Meter Mercury 233 ART-01 KRR 5(60)PC6150
Meter Mercury 233 ART-02 KRR 10(100)PC6400
Meter Mercury 233 ART-03 KRR 5(10)PC6550
Meter Mercury 233 ART-00 KR 5(7.5)PC6800
Meter Mercury 233 ART-01 KR 5(60)PC4500
Meter Mercury 233 ART-02 KR 10(100)PC3250
Meter Mercury 233 ART-03 KR 5(7.5)PC3900
Meter Mercury 234 ART-00 P 5(10)PC4800
Meter Mercury 234 ART-01 P 5(60)PC5600
Meter Mercury 234 ART-01 PO 5(60)PC3695
Meter Mercury 234 ART-02 P 5(100)PC4580
Meter Mercury 234 ART-03 P 5(10)PC6580
Meter Mercury 234 ARTM-00 PB.R 5(10)PC7590
Meter Mercury 234 ARTM-01 PB.R 5(60)PC5540
Meter Mercury 234 ARTM-01 POB.R 5(60)PC6920
Meter Mercury 234 ARTM-02 PB.R 5(100)PC9800
Meter Mercury 234 ARTM-03 PB.R 5(100)PC4500
Meter Mercury 236 ART-01 RS 10(100)PC3100
Meter Mercury 236 ART-01 RS 5(10)PC3900
Meter Mercury 236 ART-01 RS 5(60)PC2800
Meter Mercury 233 ART-01 ROL 5(60)PC9500

Example of a typical design

Devices of this brand are manufactured in a rectangular plastic case. On the front side (closer to the left edge) there is an LCD display or a mechanical wheel-type indicator. On the right side there may be a menu navigation button or the main parameters of the device may be indicated. Below is a drawing that shows the main structural elements.


Example of a typical design

Designations:

  • A – information display on which the electric meter readings are displayed.
  • B – buttons for switching display modes, for example, displaying information on various tariffs.
  • C – sticker indicating the main technical and operational characteristics.
  • D - removable panel covering the switching contacts of the device.


Photo of contacts not covered by a removable panel.
The standard dimensions of the electric meter housing (the model shown in the figure) are as follows:

  • length – 258.0 mm;
  • width – 170.0 mm;
  • height – 74.0 mm.

The dimensions of different models of electricity meters may differ from those indicated above.

As for the weight of the device, it depends on the design, in particular, the weight of modifications of the 230 model does not exceed one and a half kilograms.

The metering device is mounted on a standard DIN rail.

Single-phase electricity meter Mercury 201.7

We recommend reading our other articles

  • Interesting options for remodeling the loggia
  • How to “read” construction equipment
  • Practicality and benefits of using a soundbar
  • Construction of a private house from professionals

The Mercury 201.7 meter is a new product in the Incotex company's range of meters. Thanks to its non-dismountable body and reduced overall dimensions, the meter replaces the previous model and becomes a popular product among consumers.

Photo of Mercury 201.7 counter

Technical characteristics of the meter

Manufacturer countryRussia
StateNew
Number of tariffs1
Connection typeCombined
Rated voltage220 V
Rated current5.0(A)
Maximum current60.0(A)
Minimum operating temperature-40.0(°С)
Maximum operating temperature55.0(°С)
Length65.0(mm)
Width90.0(mm)
Height76.0(mm)
Weight0.25(kg)
Guarantee period24(months)

Briefly about self-diagnosis

Some modifications of the 200 model series have an automatic fault finding function. When detected, the display shows a message in the format E-XX, where “XX” is the error code. For example, if the message “E-18” appears on the screen, this indicates a power limit checksum error and to correct the situation it is necessary to rewrite this data.

A complete list of codes and their descriptions can be found on the manufacturer’s official website or in the instructions for the 200 series models.

Some errors can be resolved on your own, while others require calling a specialist or even returning the device to the manufacturer. For example, error E-01 indicates that the built-in battery charge has dropped to a critical threshold. It would seem nothing complicated, but in most modifications of devices for such a replacement it is necessary to disassemble the electric meter, since the device is sealed, only employees of the electric company providing the services can open it.


Battery in the Mercury 230 ART electric meter

In the described situation, the exception is modifications of the 234 series; instructions for this procedure are available in the passport for the electric meter.

Electric meter Mercury 230, modification ART2-G

The scope of application of this counter, as well as its unique characteristics are:

  1. Organization of electricity metering in 3-phase electrical networks (in this case, the device is capable of taking into account both active and reactive energy), with a standard current frequency of fifty hertz. The device can organize both unidirectional and bidirectional accounting, with the ability to transmit service information via a GSM communication channel;
  2. Equipped with a built-in tarifficator, through which it is possible to organize 4-tariff electricity metering, with the ability to work in sixteen time zones and set a special tariff for each day of the week and holidays;
  3. Organization of metering of direct-directed active electricity, simultaneously in several phases and at different tariffs;
  4. Accounting for errors associated with defects and certain losses in power lines and power transformers;
  5. Possibility of retrofitting with additional communication interfaces for organizing information exchange: GSM, infrared port, RS485;
  6. Regardless of defects in current electrical circuits, electricity metering is carried out in the direction of increasing readings;
  7. Availability of self-diagnosis function and indication of a fault code if it is detected;
  8. Possibility of accumulating information for a certain period of work (keeping an event log, saving a power profile, etc.);
  9. When using the meter as part of electrical networks operating via RS485 or CAN interfaces, remote access to the device is possible

Explanation of the electric meter marking using an example:

Mercury 230 ART2-XX PCILSDN:

  • Mercury 230 – brand and model of electricity meter;
  • AR – means that the device is designed to account for active (A) and reactive electricity (R);
  • T2 - means that the device is equipped with a built-in tarifficator (T), and accounting is possible in two directions (2);
  • XX - denotes a specific modification, where the classification between them is organized taking into account data such as current strength and voltage of the electrical network, as well as the accuracy class of the device itself;
  • P - ability to save the power profile and maintain an event log;
  • CILS - the presence of certain interfaces (C-CAN, I-IRDA, L-PLC, S-GSM);
  • DN – the ability to operate from backup power supply (D) and the presence of an electronic seal (N).

Protection against interference with the electricity meter

The design of these devices is such that it is impossible to change the readings or stop recording. As for resetting the electric meter, a record of this remains in the meter’s memory, from where the user cannot delete the information. The only thing available to him is time adjustment; there is no way around this limitation.

Unlike disk electricity meters, with digital devices, when the zero and phase are reversed, the electricity consumption will still be recorded correctly. That is, it is impossible to “rewind” the readings.

It is believed that it is possible to stop the device using a neodymium magnet. Indeed, early modifications of the 200 series had such a drawback. Modern models have protection against such interference in operation. We do not recommend testing this through personal experience, since information about an attempt to use a magnet will be entered in the device’s log, which will inevitably lead to unpleasant consequences for the experimenter.

Connection diagrams

There is nothing complicated in connecting a metering device, if you follow the instructions this procedure does not take much time. The connection diagram is available in the technical documentation that comes with each device. Using model 200 as an example, we will show how to connect a single-phase multi-tariff device.


Connecting an electricity meter Mercury 200

Contact assignment:

  • 1-5 – connection of the RS-485 or CAN interface for transmitting pulses;
  • 6 – phase input;
  • 7 – phase output;
  • 8 and 9 – connection of the neutral core.
  • 10 and 11 – telemetric output.

That is, the input to the apartment is connected to contacts 6 and 8, and the load (internal network) is connected to terminals 9 and 11.

Connecting three-phase devices.

Depending on the modification of the device, it can be connected via direct connection or through a current transformer (hereinafter referred to as CT). Let's use both options for the 230 AR as an example.


Direct connection of the Mercury 230 AR meter

If you plan to connect the device via a CT with the appropriate transformation ratio, you must first remove the jumpers between contacts: 9 and 10, 11 and 12, as well as 13 and 14. After this, you must make the connection according to the diagram shown.


Connection via three CTs

Since the purpose of pins 17-26 remains unchanged (the same as in Fig. 7), it is not given.

Before installing the protective panel covering the contacts, we recommend that you double check that the connection is correct.

Main technical characteristics of Mercury 201 meters

Also check out these articles

  • Practicality of using load-bearing corrugated sheets
  • Practicality of using modern sliding doors
  • Interior design - create your dream home
  • Practicality of using modern biofireplaces in the interior
Name of parameters Mercury
201.2 201.4 201.5201.6201.22201.7201.8
Accuracy class 1.0
Rated voltage, V 230
Rated (max.) current, A 5(60) 10(80) 5(60) 10(80) 5(60) 5(60) 5(80)
Network frequency, Hz 50
Starting current (sensitivity), mA 20 40 20 40 20 10 20
The active (apparent) power consumed by the meter voltage circuit does not exceed, W (VA)2(10)1,5(15) 2(10) 2(10)
Display device LCD LCD OUOULCD OU LCD
Gear ratio imp./kWh 6400 6400 3200 3200 6400 3200 (without pulse output) 5000 (without pulse output)
Power Line Interface (PLC) +
Operating temperature range, C -40… +55 -45… +75
Overall dimensions, (DxWxH) mm 65x105x105 66x77x91
Weight, no more than, kg 0,35 0,25
Calibration interval, years 16
Manufacturer's warranty, years 3
Service life, years 30

Instrument verification

In accordance with the norms of Federal legislation, metering devices are subject to mandatory verification. It can be primary and periodic. The first is performed directly at the factory where the products are manufactured. The second is periodically during operation after the expiration of the verification interval; information about it is indicated in the technical passport.

Sometimes an unscheduled procedure may be scheduled before the verification period expires. The following cases are provided for this:

  • loss of a document indicating completion of a planned procedure;
  • after the device has been set up or adjusted, for example, after repair;
  • when installing a new device.

For verification, standard instruments or special installations are used, such as the Mercury 211 multifunctional device. The electronic device circuit includes a source of fictitious power and a reference (model) electric meter. Such a device can simultaneously test up to 8 devices.

After verification, information about this is entered into a special register, which contains the device number, year of manufacture and test date.

Choosing an electric meter

First of all, you need to make sure that the device matches the connection diagram; it can be single- or three-phase. Next, you should take into account the features of the box in which the control device will be installed. The device must be placed in such a way that readings can be taken without opening the electrical cabinet cover. That is, the window in its door should be located opposite the display or mechanical indicator.


In such panels, readings are taken with the doors closed

Please note that when replacing outdated disk devices with devices from the 20X model range, a problem often arises when the device’s information panel is not visible through the dashboard window. The problem can be solved by choosing Mercury 200 as a replacement; the manufacturer specially developed this model for installation in old-type apartment panels, which significantly simplified installation and made it possible to read readings without opening the box.

Currently, Incotex has stopped producing devices operating on the induction principle, so only electronic modules are available for purchase.

It makes sense to purchase multi-tariff devices only if such a payment scheme is used in the region of residence and it is possible to use household appliances at night.

Decide on functionality. Of course, an electric meter with memory is more convenient and allows you to compare electricity consumption with the previous period or any other month. How relevant this is is for the consumer to decide, but given how much such devices cost, it is better to get this information from receipts. The same applies to models equipped with a remote control; its need is greatly exaggerated.

There is no point in purchasing a model capable of transmitting readings to the electric company if the latter does not have this capability.

It is debatable how necessary it is to purchase a device, for example, the 201 series, where after installing special software, it becomes possible to call the office to obtain detailed information. Additional modules that make up such an electric meter lead to a significant increase in the cost of the device. Again, as practice shows, the simpler the device, the longer it will last.

Now let's move on from general advice to specifics:

  • Each Mercury electricity meter must be equipped with a passport and technical documentation, which indicates the capacity of the electricity meter, a description of how it works, a connection diagram and other useful information. The technical documentation should include an operating manual that describes in detail how to correctly take readings, information about the verification interval, etc.

In the absence of a passport, the device will not be able to be registered and, accordingly, operation will be impossible.

  • There must be a hologram on the electric meter, as well as a factory seal.
  • Compare the signs and numbers on the electric meter with the serial number indicated in the passport.
  • Check that the warranty card is filled out correctly, otherwise the warranty for the electric meter may be invalidated. If such a device fails or does not work correctly (for example, it overestimates the significance of the readings, beeps, consumes a lot of energy from an additional source, etc.), then problems may arise with its replacement or repair.

Please note that inflated readings (the device has more kW than it actually consumes) are not uncommon. This indicates that the device is not adjusted correctly.

Source

Meter Mercury 201.8 TLO

Electricity meter Mercury 201.8 TLO is designed for metering active and reactive energy in multi-tariff (up to 4 tariffs) or single-tariff modes.

Explanation of the designation:

  • T-multi-tariff
  • L - PLC-II modem
  • O - built-in relay

Photo of the Mercury 201.8 TLO meter

Technical characteristics of the meter

name of parametersQuantities
Accuracy class for measuring active energy of reactive energy1,0 2,0
Rated voltage, V230
Established operating voltage range, V Extended operating voltage range, V Limit operating voltage range, V207…253 184…264 0…264
Rated (max) current, A5(80)
Active (apparent) power consumed by the voltage circuit, no more than W (VA)2(10)
Total power consumed by the current circuit, no more than VA0,1
Permissible overcurrent for 10 ms, A - for IMax = 80 A2400
Starting current (sensitivity), A0,020
Tariff parameters:
number of tariffs number of tariff zones within a day number of types of days number of seasons
1…4 16 8 12
Exchange rate, bits/second:
- via optical port;
9600
Gear ratio of the optical test output: — in telemetry mode, imp/kW, [imp/(kvar*h)] — in verification mode, imp/kW [imp/(kvar*h)]5000 10000
Data safety during power interruptions, years - permanent information - operational information40 10
Data protection1. Address access and hardware protection of memory of metrological coefficients.
2. Log of communication sessions via digital interfaces.
Temperature range, °Cfrom - 45 to +70
When operating meters at temperatures below -20, partial loss of LCD functionality is allowed.
LCD capacity, kW*hXXXXXXX,xx
MTBF, hours220000
trouble-free operation, hours7000
service life, years30
Interverification interval, years16
Weight, kgno more than 0.6
Dimensions (length, width, height), mm128*89,5*64,7
Manufacturer's warranty3 years
Rating
( 2 ratings, average 4.5 out of 5 )
Did you like the article? Share with friends:
For any suggestions regarding the site: [email protected]
Для любых предложений по сайту: [email protected]